Flight of steps
Contents |
[edit] Introduction
‘Flight’ is a term used in building design and construction to denote a continuous sequence of steps (or risers) connecting floors, landings or intermediate landings. The typical width of a flight in a domestic setting is around 850mm or more.
The arrangement and number of flights in a staircase will depend on the type of stair.
A ‘straight flight’ will have no intermediate landings and comprise a continuous series of risers between floor levels. See note below on maximum allowable risers in a flight.
A quarter-turn stair (sometimes called a ‘dog-leg’ stair) features a quarter-turn landing situated between flights. This may be located at any point on the staircase, from which point the second flight changes direction by 90 degrees to the left or right leading to the next floor above. In properties where space is at a premium, the landing may be replaced by a series of winders (wedge-shaped steps in plan) which then makes the stairway a continuous single-flight stair.
A half-turn stair usually involves a half landing between two flights and allows a 180-degree change of direction. An alternative arrangement to achieve 180-degree travel, space permitting, is to have two quarter landings in a configuration of flight-QL-flight-QL-flight; this may also form an open-well stair.
Whether a quarter- or half-turn stair, the flights can be supported on the landings.
The Approved Documents of the Building Regulations set out additional guidance and require compliance with various criteria concerning flights.
[edit] Length of flight
Stairs with more than 36 risers in consecutive flights should have at least one change in direction between flights. For buildings other than dwellings, the maximum number of risers between landings should be 16 for utility stairs and 12 for general access stairs. There should not be any single steps.
There are more complex requirements for tapered, spiral, alternating tread and helical stairs. Refer to Approved Document K.
For more information see: Landings in buildings and Maximum length of a flight of stairs.
[edit] For all buildings
At the top and bottom of every flight, landings should be provided which have a width and length at least as great as the smallest width of the flight.
Full requirements for flights and stairs generally can be found in the following Approved Documents:
- Approved Document B – Fire safety.
- Approved Document K – Protection from falling, collision and impact.
- Approved Document M – Access to and use of buildings.
[edit] Related articles on Designing Buildings Wiki
- Accommodation stair
- Approved Document B
- Approved Document K
- Approved Document M
- Firefighting lobby
- Guarding
- Ladder.
- Landings in buildings
- Maximum length of a flight of stairs
- Means of escape
- Protected stair v escape stair
- Protected stairway
- Railings
- Spiral stairs and helical stairs
- Stair design
- Stairs going
- Stairs nosing
- Stairs riser
- Stairs tread
- Types of stairs
- When to install a staircase during the construction process.
- Width of doors stairs and escape routes.
Featured articles and news
International Electrician Day, 10 June 2025
Celebrating the role of electrical engineers from André-Marie Amperè, today and for the future.
New guide for clients launched at Houses of Parliament
'There has never been a more important time for clients to step up and ...ask the right questions'
The impact of recycled slate tiles
Innovation across the decades.
EPC changes for existing buildings
Changes and their context as the new RdSAP methodology comes into use from 15 June.
Skills England publishes Sector skills needs assessments
Priority areas relating to the built environment highlighted and described in brief.
BSRIA HVAC Market Watch - May 2025 Edition
Heat Pump Market Outlook: Policy, Performance & Refrigerant Trends for 2025–2028.
Committing to EDI in construction with CIOB
Built Environment professional bodies deepen commitment to EDI with two new signatories: CIAT and CICES.
Government Grenfell progress report at a glance
Line by line recomendation overview, with links to more details.
An engaging and lively review of his professional life.
Sustainable heating for listed buildings
A problem that needs to be approached intelligently.
50th Golden anniversary ECA Edmundson apprentice award
Deadline for entries has been extended to Friday 27 June, so don't miss out!
CIAT at the London Festival of Architecture
Designing for Everyone: Breaking Barriers in Inclusive Architecture.
Mixed reactions to apprenticeship and skills reform 2025
A 'welcome shift' for some and a 'backwards step' for others.
Licensing construction in the UK
As the latest report and proposal to licence builders reaches Parliament.
Building Safety Alliance golden thread guidance
Extensive excel checklist of information with guidance document freely accessible.
Fair Payment Code and other payment initiatives
For fair and late payments, need to work together to add value.
Pre-planning delivery programmes and delay penalties
Proposed for housebuilders in government reform: Speeding Up Build Out.
High street health: converting a building for healthcare uses
The benefits of health centres acting as new anchor sites in the high street.